The variation notice arrived when the frame was up. A couple building their first home on a sloping block near Morisset, in Lake Macquarie, were told by their builder that the provisional sums in their fixed-price contract, the allowances for rock excavation and a retaining wall, had run $38,000 over.
Their question was the one most people ask at this point: does the construction loan simply cover it?
The situation
The couple bought the land for $330,000 and signed a building contract for $510,000, a total cost of $840,000. As first home buyers, the land price sat below the $350,000 threshold for vacant land under the NSW First Home Buyers Assistance Scheme, so no transfer duty came out of their savings. The combined land and build price was above the $750,000 cap for the NSW First Home Owner Grant on a new home, so no grant was in the numbers.
The lender valued the plans at $860,000 on completion and approved a loan of $672,000, which was 80% of the total cost. The couple’s own $168,000 went in first: the land deposit and balance, then the slab stage. After that, they had about $22,000 left in savings.
Variations like this one sit against a wider backdrop: JLL’s 2026 construction costs index found that building costs in Australia are still rising faster than general inflation, even as cost growth steadies.
What happened
The lender’s position was straightforward. It had approved a loan against a contract of $510,000, and it releases progress payments against that contract, stage by stage. The $38,000 was not part of what it had assessed, so it was not part of what it would pay.
That left two routes. The couple could pay the variation from their own funds, or apply to increase the loan. With $22,000 in savings, the first route alone did not cover it, so they needed both.
An increase is a fresh assessment rather than an adjustment. The lender asked for the signed variation and the builder’s revised contract price, re-tested the couple’s income and expenses at its current assessment rate, which had moved since the original approval, and asked the valuer to update the on-completion value.
The valuer moved the figure from $860,000 to $865,000. Rock removal and a retaining wall make a sloping block buildable, but they add little that a buyer of the finished home would pay extra for. The total cost was now $878,000, and the lender lends against the lower of cost and value. At 80% of $865,000, the maximum loan became $692,000, an increase of $20,000.
The remaining $18,000 came from the couple’s savings, and the lender required it to be paid to the builder before it would release its next payment. The lock-up payment was released about three weeks after the builder’s invoice, once the increase was in place and the couple’s share had gone in. They finished the build with around $4,000 in reserve rather than $22,000.
What mattered
The contract is what the lender funds. Progress payments follow the contract the lender approved. Anything outside it, whether a provisional sum that runs over or an upgrade chosen on site, is the borrower’s to fund first or to bring back to the lender for assessment.
The valuation sets the ceiling, and it does not rise dollar for dollar with cost. Site costs in particular often add less to the on-completion value than they add to the price. On a sloping block, that gap is where the extra money has to come from.
Funds to complete are counted again mid-build. The couple’s original contribution was $168,000. The variation changed that figure to $186,000, and the lender checked the new figure the same way it checked the first: verified savings, paid in before its own funds.
Provisional sums are estimates. A fixed-price contract can still carry allowances for work that cannot be priced until the ground is open. Knowing which items are provisional, and how large they are, shows how much of the price is actually fixed.
Serviceability is re-tested at current settings. An increase is assessed on the lender’s current rate and the household’s current position, not the position at the first approval.
In situations like this
We often see variations arrive at frame or lock-up stage, once the site work is finished and the true cost is known. What typically decides whether a variation is a paperwork step or a full reassessment is the structure set at approval: a contingency built into the loan, or savings deliberately held back after the contribution. Where neither is there, the outcome depends on the updated valuation and the servicing result on the day the variation lands.
Understanding
A construction loan funds the contract the lender approved. When the build price moves, the difference is assessed again, against an updated valuation and current servicing, and the borrower’s share goes in first. Understanding how this is assessed before you apply puts you in a better position.